Home About Us Our Services Doing Business with us Resources Corporate Social Responsibility Our Partners HSEContact & Inquiries
OTHER LINKS
» Liberia's Oil Sector
The LPRC OILERS
LPRC IN PICTURES




















  GASOLINE (PMS) - Retail
   US$ 3.26 US GL    GASOLINE (PMS)
  GASOLINE (PMS) - Whole sale
   US$ 3.08 US GL    GASOLINE (PMS)
  FUEL (AGO) - Retail
   US$ 3.26 US GL    FUEL (AGO)
  FUEL (AGO) - Whole sale
   US$ 3.08 US GL    FUEL (AGO)
  KEROSENE (JET-A1) - Retail
   US$ 3.41 US GL    KEROSENE (JET-A1)
  KEROSENE (JET-A1) - Whole sale
   US$ 3.41 US GL    KEROSENE (JET-A1)

 « Our Projects »  Planning & Project Review 2013-2014
PLANNING & PROJECTS REVIEW
 
The Liberia Petroleum Refining Company (LPRC) basic objectives as established by the 5-Year Strategic Plan is to restore pre-war capacity, meet statutory mandate, increase revenue and strengthen the position and image of the company. 
 
One of the Strategic Focus Areas is the Technical / Operational Services of the Operations Division that is the lifeblood of the company.   Its operations of 2014 are reported as follows:  
 
PST Rehab & Expansion Project – Contractor: Motherwell Bridge Ltd.(MBL)
 
The following projects were completed by MBL:
 
Project Objective: Rehabilitating and expanding the Product Storage Terminal (PST)
Project Cost:  22.4 million
Payment Update:  Dec.2013 – 11.0 million
Project Status: Project Terminated in November 2014

Reason for Termination: Notice of Force Majeure consistent with sub-clause 19.2 of the contract concerning the EVD surge in March 2014.
 
 
Tank
Status
% Completed 2013
% Completed 2014
Tank 2
(800m3 ) (ATK)

Foundation and activity progress

36.2 %
54.0%
Tank 3
 (10,000m3)
 (AGO)
Foundation and steel work (shell erection) completed at
96%
99.15%
Tank 4
 (9,540m3)
(PMS)

Foundation and shell erection completed at..

94.95 %
97.75%
Tank 9
 (5,550m3)
(JET-ATK)
Foundation and erection completed at..
89.80%
90.98%
Tank 11 / Slop Tank
(79m3)
Work completed at..
86.00%
91.30%
Fire Water Tank
(2,210.5m3)
Work completed at..
96.30%
99.15%
Bund Wall / Drainage

Work completed, 3rd Phase casting in progress around Tank 1, 3, and 9.

52.0%
60.40%
Bund Slab Pavement

Work completed, Steel mat laid at Tank 3

28.10%
48.0%
Jetty Supply Lines & Walkway Project

Supply pipeline AGO & JET-A1

38.95%
39.15%
Jetty Supply Lines & Walkway Project
(PMS-Green Coast)        75 pipe sleepers constructed at…
90.00 %
 
Tanks 1,5,6,7,8 (Old tanks to be renewed)
Geotechnical examination of soil around tanks undertaken.
0%
0%
Tank Farm Existing Piping
 
12.12 %
12.12 %

 

Modernization and Rehabilitation of Ganta Oil Terminal (GOT) – Contractor: Petro Trade/Sultan Steel

 
Project Objective:   Maximize economic recovery & fuel security in leeward counties.
 
Project Cost: US$ 3,418,106.00
Project Field Monitoring & Observations (December 2013, Environmental studies in progress;

Project Commencement Date: expected to be completed in 2015;

 

 

 
Rehabilitation and Expansion of the Crude Storage Terminal (CST), - Contractor: LUTECH CONEX
 

Project Objective:   Facility will be used to supply Heavy Fuel Oil (HFO) to LEC and others.;
Project Cost: US$ 25,000,000

Project Field Monitoring & Observations 
Project Completion Date: expected to be completed in 2015

 

 

 

 
Construction of a Parking Lot Pavement - Contractor:
 
 
Project Objective:   Adhere to loading and environmental standards.
Project Cost: US$ 574,190.84

Project Field Monitoring & Observations (December 2013).- completed 1st Phase;
December 2014 - 2nd / 3rd Phase Completed

 

 

 

 

Project Objective:   New PMS line installation from Jetty to Tank Farm.
Project Cost: US$ 29,500

Project Field Monitoring & Observations (December 2013).- completed 90%;
December 2014 – Completed 100%

Truck Entrance Sliding Gate

Project Objective:  Enhance smooth entry and exit of trucks accessing the PST.
Project Cost: US$ 9, 508.00
Project Field Monitoring & Observations (December 2014).- Project completed ;
 